Euston Road Energy Centre and District Heating Network

July 2013: After several years building the case, it is hugely positive to see that Camden have now released a tender for a £5.7m  decentralised energy network along Euston Road. The tender document sets out that:

“The London Borough of Camden has identified a cluster of four communally heated estates in Somers Town, Kings Cross, London NW1 which are in close proximity to the Francis Crick Institute, a new major biomedical research facility due to be completed in 2015/16. The aggregated volume of heat and electrical demands for the estates and Francis Crick Institute has been assessed by Arup on behalf of the Decentralised Energy for London programme and is considered to provide an excellent opportunity for a phased decentralised energy network. Full planning consent for a centralised energy centre has been secured and full Cabinet approval has been secured from the London Borough of Camden to procure the project.”

The tender information goes on: “The scheme will be commissioned and delivered in the following phases:

  • Phase 1 – would see a heat only district heating project design, built, operated and maintained for the four estates via a district heating network connected to a central energy centre for which full planning permission has been granted.
  • Phase 2 – Once the Francis Crick Institute (“the Crick”) establishes a sufficient electrical demand (envisaged 2016) and an agreement is reached, Camden Council may commission the installation, operation and maintenance of a c.1MWe CHP unit (indicative size only) at the Phase 1 Energy Centre with a direct electrical connection to the Crick. Upon Phase 2 commission, the CHP system shall then also be the primary source of heat supply to the district heating network installed in Phase 1.
  • Phase 3 – Camden Council intends to extend the network to connect to Council regeneration planned for the wider Somers Town area over the next 4-5 years. This phase will not be procured within this exercise. However, the design and build under Phase 1 will include the expansion capacity to support future district heating demands.

The proposed heat route can be seen on the planning application for the CHP here. An open day will be held for bidders on Monday, 5 August 2013.

This entry was posted in Decentralised Energy, News and tagged , , , . Bookmark the permalink.